SCRI 132kV TERNA

SCRI 132kV TERNA

Company: ABB S.p.A.
Customer: TERNA S.p.A.
Facility: Railway
Year: 2020
Site: Montebello Vicentino
Value: €400k


Scope of Work

  • Engineering of layout and plant modifications
  • Coordination of civil works in constrained conditions
  • SCRI maintenance and pre-deployment verification
  • Supervision of installation and commissioning
  • Technical training for operators
  • Three-year O&M contract management

Project Overview

Deployment of a 132 kV SCRI (Rapid Installation Compact Substation) mobile unit to ensure power continuity for the Montebello Vicentino railway station, temporarily bypassing the existing RFI substation and upgrading control systems to Terna standards.
The project was characterized by significant logistical challenges, including the transport and installation of the mobile substation in a constrained environment, as well as complex modifications to protection and control systems required for full compliance with Terna specifications.

EnerG-Project
Panoramica privacy

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.