ESS 132kV MARCEGAGLIA

ESS 132kV MARCEGAGLIA

Company: ABB/Hitachi Energy Italy S.p.A.
Customer: Marcegaglia Ravenna S.p.A.
Facility: Steel
Year: 2021-2023
Site: Ravenna factory
Value: €1,5M

Scope of Work:

Engineering, procurement, construction and commissioning for the supply of:

  • N.1 new bay for grid connection (revamping)
  • N.1 new bay for the connection of a new cogeneration plant (extension)
  • Complete renovation of the entire protection and control system for 5 bay AIS substation
  • Revamping of MV relays for the integration in the new system and the implementation of coordinated logics and protection functions
  • N.6 RTU remote system to monitor and control three different FV plants and three cogenerators

Project Overview:

The project required complex planning and execution to minimize disruption to ongoing plant operations. Activities were carefully phased to reduce outage durations while ensuring high safety and quality standards.

Particular attention was given to integrating new systems within an existing live substation and coordinating multiple workstreams across grid, cogeneration, and photovoltaic assets.

Through detailed scheduling and close coordination with the customer, high service continuity was maintained and production losses were kept to a minimum.

EnerG-Project
Panoramica privacy

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.